Energy: Phase 3 Solar Panel Project – November Update

Summary  of the estimated dates of construction of Phase 3 Solar Panel Project at Newton schools. Please note that dates are still subject to change depending upon a number of factors.

Source:  Facilities Updated to the School Committee on Nov 18, 2019   

1. Zervas and Education Center roof projects have started and will be completed by the end of the year.

2. North High School parking canopies. There are two canopies being constructed, one at Lowell Avenue and one at Walnut Street. This will be done in two phases with foundation work done mostly during the April 2020 School Break and the installation of the canopies during the summer. This proposed schedule should greatly minimize alternative parking as was originally foreseen.
– The foundations will be built over the spring break week. The Lowell Ave work will spill over into the two weeks after spring break. The Walnut Street work will be done before students
return from spring break. There’s a plan for alternative parking for these two spillover weeks.
– The canopies and solar panels will be erected during the summer 2020 and alternative parking is not anticipated at this point.

3. Cabot, Carr, and Angier roof projects are currently schedule for the spring. A specific schedule will be provided when available. These roof projects will be done with minimal disruption to school activities. Material will be craned to the roofs on a Saturday and will be out of the way once they are on the roof. Materials will be on site for a few days before craning but we will coordinate with the Facilities Department to place these materials in an acceptable location while they wait for craning.

4. Education Center parking canopies are planned for the spring.

According to Mayor Fuller, “Solar panels are currently being installed on the roof of
the Zervas Elementary School. When the solar array comes online in December, it will provide 42 percent of the school’s electricity.”

Zervas Solar Panels 2019